MITTRA has been actively involved in implementing water resources development (WRD) programs which is an integral part of natural resources management. WRD is implemented in all development programs. The activities of Water Resource Development include spring development, diversion channels, well development, lift irrigation schemes, Jalkunds, promoting use of treadle pumps etc.

Benefits:


WRD program helps to:
  • Improve the survival of plants in wadis
  • improved the crop production
  • provide drinking water for animals and humans.


Cummulative Progress of WRD Activities

The cumulative progress achieved so far is given below.

Particulars

Cumulative

During

Cumulative

During

Cumulative

2013-14

2014-15

2014-15

2015-16

2015-16

Temporary check dams

3921

 

3921

4

3925

Permanent check dams

116

11

127

18

3925

Spring Development

1633

1

1634

1634

Jalkund

1544

 

1544

1544

Lift irrigation schemes

50

 

50

50

Well development

3053

300

3353

12

3365

New well development

396

 

396

9

405

Support for Drums / Drips

12403

 

12403

12403

Treadle Pumps

1371

 

1371

1371

Roof top Water harvesting

36

 

36

36

Diversion channels

46

11

57

57

Support for Drinking Water Unit

658

 

658

2

658

Farm Pond

4

4

Bodi Distillation

83

83



    Next